Custom Cabinet Lead Time: The 90-Day Calendar From Deposit to Site

2026-11-18

“What’s your lead time?”

It’s the most common line in an enquiry email and the least informative one. No factory can answer it honestly in a sentence, because there are eleven steps between deposit and site delivery and four of them aren’t in the factory’s hands. Same factory, same cabinets: the number can be 62 days or 118, and the difference isn’t capacity — it’s when you sign.

So this isn’t a page that says “45 days to ship”. It’s a reverse calendar: start from the day you need cabinets on site and count backwards, with what has to happen at each step, who signs, and what a single day of slippage costs. Use it and you’ll know whether the project is late before steel is cut, instead of after the vessel sails.

The day counts below come from our records on North American, Australian, Middle Eastern and European projects, covering both single homes and multi-unit batches. A simple one-category order runs faster; a whole-house package (kitchen plus wardrobes plus vanities plus wall panels) sits at the top of every range.

First, Dismantle the Number “45 Days”

What a factory quotes as 45 days usually covers one stretch: material arriving, to finished goods crated. It excludes drawing approval, sampling, vessel booking, ocean transit, customs and final delivery. Those four together often run to 1.5× the production period.

An honest lead time has five stages:

StageActual daysControlled by
1. Drawing freeze and sampling10–18 daysClient / design team
2. Material pull and panel processing10–20 daysFactory
3. Assembly and finishing (incl. cure)18–26 daysFactory, and not compressible
4. QC, crating, booking8–14 daysFactory + forwarder
5. Ocean, customs, delivery18–45 daysCarrier + broker

Add the ranges: 64 to 123 days. That’s why “45 days” was never a lead time — it’s part of stages three and four.

sjumbo-turnkey-townhome-kitchen-grey-cabinets.jpg

Stage 1: Drawing Freeze and Sampling (Day 0–18)

The most underestimated stage, because it barely touches factory capacity while determining everything after it.

From your architectural or interior drawings we produce shop drawings: every carcass dimension, bay layout, hardware position, closure detail, light groove location. Five to seven days. Then the approval loop begins — client, designer, project manager, sometimes a clerk of works — and each round takes three to five days to come back. Historical average: 1.5 rounds, so about a week.

Sampling runs in parallel. One door, one edge-banded section, one finished panel: 7–10 days. If the project specifies a custom colour — a RAL number, or a board sample the client supplied — the sample has to come first, because colour gets judged physically under the light of the actual site. Screens lie.

The real output of this stage isn’t the sample. It’s a signature: drawing freeze. Every change after that point is priced by how many panels are already cut. This is where most disputes are born — the client thinks moving a drawer is a small thing; the factory sees forty panels with holes already drilled.

Stage 2: Material Pull and Panel Processing (Day 10–20)

Material and production overlap, because nobody waits for the full kit before starting.

Stocked materials — standard melamine, PET, common plywood thicknesses — land in three to five days. Imported veneer, sintered stone tops, custom-colour lacquer substrates: 10–15 days, occasionally waiting on a container. The risk here isn’t the factory, it’s stock status. If the project specifies one brand’s particular colour code, ask about availability before discussing dates.

Panel processing takes 8–12 days: cutting, edge banding, drilling (32 mm system holes), grooving (back panel, light channels), shaped components. Pure capacity, so it can be compressed with overtime — up to a point. Edge banding speed and glue temperature have a process window, and banding run hot is banding that lifts in year two.

Stage 3: Assembly and Finishing (Day 18–26, Not Compressible)

Assembly and dry fit: 5–8 days. The value here is the dry fit itself — standing a whole run up in the factory to check door gaps, drawer reveals, corner joints, light groove alignment. A serious dry fit means less site rework. Skip it to save three days and you’ll typically spend three weeks recovering on site.

Finishing is the least compressible stretch in the entire chain. Lacquer, for example: primer, sand, topcoat, four to six passes, each needing drying and sanding — 8–12 days of process alone. And then it isn’t finished: the film needs 7–10 days to cure. Crate it early and you open the box to imprinting and blocking.

Why Cure Time Is Not a Scheduling Variable

This is the stage we’re most often asked to “work with”, and the one we can’t. Cure time tracks humidity: in a coastal wet season, seven days isn’t enough — plan on ten to twelve. Cutting cure to catch a vessel pays out as a full batch of door rework. On a 200-unit project, the rework bill would cover two more kitchens.

Veneer and melamine need no cure, which saves 7–8 days. That is the only real way finish choice affects lead time, and it has nothing to do with how expensive it looks.

sjumbo-turnkey-townhome-bathroom-vanity.jpg

Stage 4: QC, Crating, Booking (Day 8–14)

QC takes two to three days: sampling ratio, appearance, dimensional check, hardware function, colour comparison with the batch laid out together under standard light.

Crating takes three to five. Shaped parts, glass and stone tops get individual timber cases; standard panels get five-layer corrugate and corner protection. We went through that detail separately in how steel-and-timber crates get 3 m cabinets to the other side with zero breakage.

Booking is the real bottleneck of this stage, and it isn’t in the factory. In peak season — August to October, the pre-holiday restocking window — space needs booking four to six weeks ahead. Book late and you either don’t sail or you pay double. Whole-house packages are bulky, so how many 40HQ containers you need and how they’re loaded drives everything; the arithmetic is in CBM calculation and 40HQ loading rates for consolidated whole-house orders.

Stage 5: Ocean, Customs, Delivery (Day 18–45)

Entirely destination-dependent, entirely outside the factory, and entirely part of your lead time:

DestinationSailing daysNote
US West Coast14–18Fastest mainlane
US East Coast30–38Via Panama or transhipment
Northern Europe28–35Scandinavia slightly longer
Australia12–18Sydney / Melbourne
Middle East18–25Mostly Jebel Ali
UK30–35Watch clearance times

Customs takes 3–7 days, provided the documents are complete. Incomplete documents are the most common non-production delay in the category: packing list, commercial invoice, certificate of origin, FSC certificate, formaldehyde test report, ISPM-15 treatment evidence for timber packaging. One missing page and the container sits at the terminal.

Final delivery to site: 2–7 days, depending on whether the project is urban or regional, whether there’s unloading access, and whether a 40-foot truck can get in.

The Reverse Calendar: Seven Signatures Between You and Handover

This is the part worth printing. Assume your required on-site date is Day D. Read the table backwards:

MilestoneWhenWhat happensWho signs
Drawing freezeD-95Shop drawings approved, incl. hardware schedule, closures, light groovesClient / design
Deposit and material POD-88Payment, materials ordered incl. custom colour codesProcurement
First pieceD-75One complete carcass assembled and approvedProject manager
Finish approvalD-60Physical sample judged under site lightClient / design
Vessel bookingD-52Space locked, container type set by CBMForwarder
Pre-shipment inspectionD-40Sampling, photography, colour checkThird party or client rep
Documents completeD-32Full clearance setDocumentation
Container loadedD-28Loading, seal, empty and full container photosFactory
Port arrivalD-12Bill exchange, declarationBroker
Delivery to siteD-5Unload, count, distribute by floorSite
Installation completeD-0Closures, door adjustment, clean-upInstaller

Built on 16 days of sailing (US West Coast or Australia). European projects shift the whole table 14 days later, which puts the deposit at D-109.

sjumbo-turnkey-townhome-walk-in-closet.jpg

The Seven Dates That Actually Decide It

Eleven milestones in the table, but only seven are unrecoverable if missed. In order of danger:

One: finish approval (D-60). The most common and most expensive delay in the category, for a very plain reason — colour has to be judged physically, physical takes time to make, the client wants to see it twice, and three weeks pass between viewings. By the time it’s signed, the finishing line has moved on to another order. In our records, over 40% of late projects lost time here.

Two: vessel booking (D-52). Space is an external resource. Book a week late in peak season and you may wait two extra weeks for a sailing. Most often missed because it looks like the forwarder’s job when it’s actually procurement’s.

Three: drawing freeze (D-95). Every day late here pushes all eleven milestones a day, without exception. The cheapest day in the schedule and the most expensive one to lose.

Four: first piece (D-75). Bulk cutting waits on it. A failed first piece usually means the drawings are wrong, which sends you back to milestone one.

Five: documents complete (D-32). One missing certificate of origin and the container waits at the terminal, accruing storage. Zero technical content, pure checklist discipline.

Six: pre-shipment inspection (D-40). Problems found here can still be fixed in the factory. Problems found after the vessel sails get fixed by air freight or by waiting for the next batch.

Seven: delivery to site (D-5). If the site isn’t ready — floor unfinished, lift not commissioned, loading bay occupied — the cabinets need somewhere to live. The cost isn’t time, it’s money: storage, re-delivery, and worst of all, a dispute with no clear owner.

Three Schedules That Broke, and the Day They Broke

No invented case studies — three we worked through.

A 40-unit townhouse project in Australia: the client changed the shared-area carcass from light grey to warm grey on day 58. At that point 40% of the door faces had their first topcoat. Cost: eleven days and a full refinish. That project is why we now require the colour sample signed before freeze. The method is written up in four steps to zero colour difference across a 50-unit residential project.

A hotel in the Middle East: every internal milestone on time, and booking landed in peak season anyway. Rolled twice — seven days, then twelve. The container waited nineteen days at port while the factory had nothing left to do. Since then, hospitality projects here book space before finishing starts.

A US project: shipped on time, cleared on time, delivered on time, and couldn’t get in — the self-levelling screed had just been poured and hadn’t reached working strength. Nine days in a container yard. Storage plus re-delivery came to more than the installation cost of the batch.

The common thread: none of the three broke in production. All three broke at the interface between production and site.

What Can Be Compressed, and What Cannot

If the schedule is short, check this list first.

What Gives

Panel processing (overtime, 8 days to 6, quality intact); material pull (switch to a stocked finish, saves 5–7 days); crating and booking (lock space early, run in parallel); customs (pre-declaration); delivery (air freight for missing items).

What Doesn’t

Finish cure (7–10 days; less than that is trading rework for time); dry fit (save three days, repay three weeks); QC (48 hours is the floor); sailing days (not negotiable).

One rule of thumb worth keeping: compressing a whole schedule by more than 15% reliably produces quality problems, because roughly 15% is all the slack that exists. Beyond that you’re taking it out of cure and dry fit.

If You’re Already Late: Four Moves, In Order

One: separate “the whole batch is late” from “the critical pieces are late”. If only tops or glass doors are behind, ship the carcasses and air freight the critical items. Holding everything for the last part is the most expensive option available.

Two: change the delivery rhythm, not the delivery date. Multi-unit projects can ship by floor or by block — get the ready portion to site so the install crew keeps working instead of standing down.

Three: change the finish. If the delay comes from cure time or a custom colour, moving to a stocked melamine in the same family saves 8–10 days at the cost of one grade of feel. That decision belongs to the client, not to a factory recommendation.

Four: re-sign the milestones. Put the new dates in a contract annex, not in an email. Late projects suffer less from the delay itself than from everyone believing it arrives “next week”.

A Milestone Sheet You Can Paste Into the Weekly Report

A project manager doesn’t need a lead-time promise. They need a status they can check every week:

MilestonePlanned dateStatusOwnerNote
Drawing freeze
Deposit received
First piece approved
Finish signed
Space confirmed (vessel + voyage)
Production complete
Inspection passed
Container loaded (seal no.)
Arrival / clearance
Delivered to site

Ten rows, filled once a week, outperform any letter of commitment. It turns lead time from a number into ten actions someone can be held to.

The Four Questions We’re Asked Most About Lead Time

How long from deposit to site, typically?

75 to 110 days, depending on destination and finish. US West Coast and Australia sit near the bottom, Europe and the Middle East near the top; lacquer adds 8–10 days of cure over melamine.

What’s the fastest realistic schedule?

Stocked finish, stocked material, no consolidation, US West Coast: 62 days to port, about 72 days to site after clearance and delivery. A promise below that is being paid for out of cure time or dry fit, and both get repaid at installation.

Does the clock start at deposit?

No — it starts at drawing freeze. A deposit reserves capacity and material; until drawings are frozen, nobody can cut. Which is why we suggest putting the freeze date in the contract rather than “XX days from deposit”.

What slows projects down most?

In our records: finish approval (40%), vessel booking (25%), drawing revisions (20%), incomplete documents (10%), site not ready (5%). Production itself is rarely the cause.

sjumbo-turnkey-townhome-living-room-wall-system.jpg

Send Us Your Handover Date and We’ll Count Backwards

Give us one date — the day you need cabinets on site — and we’ll fill this calendar in for your project: where each milestone lands, who signs, which materials need locking early, and where there’s room to compress.

Multi-unit projects are worth doing this for first, because batch delivery schedules behave differently from single homes and the risks sit in different places. That experience is written up in risk control for multi-family cabinetry, from CAD drawings to mass delivery; the inventory side is in how modular cabinetry cuts 20% of inventory complexity. Australian build-to-rent work carries extra compliance milestones, covered in cabinetry delivery for build-to-rent projects in Australia.

Send the date. We’ll send back a filled-in calendar.